Contract No: Hy/2019/18 Wanchai Development Phase II and
Central Wanchai Bypass Sampling, Field Measurement and Testing Works (Stage 4) Environmental Permit no.
EP-356/2009, Further
Evironmental permit nos. FEP-03/356/2009, Fep-04/356/2009 AND FEP-07/356/2009 Monthly Environmental Monitoring & Audit Report
- MARCH 2020 -
|
CLIENTS: |
|
Civil Engineering and Development Department and
Highways Department |
Lam
Geotechnics Limited 11/F Centre Point 181-185
Gloucester Road, Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
15 April 2020 |
|
|
2.2 Scope of the Project and Site
Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact
Personnel
3 Status of Regulatory Compliance
3.1 Status of Environmental Licensing and
Permitting under the Project
5.3 Water quality monitoring Results
6.4 Review of the Reasons for and the
Implications of Non-compliance.
6.5 Summary of action taken in the event of
and follow-up on non-compliance
7. Cumulative Construction Impact due
to the Concurrent Projects
9.
Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary
of Water Quality Monitoring Exceedances in Reporting Month
Table II
Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in
Reporting Month
Table
2.1 Schedule
2 Designated Projects under this Project
Table
2.2 Details
of Individual Contracts under the Project
Table
2.3 Contact
Details of Key Personnel
Table
3.3 Summary
of submission status under FEP-02/356/2009 Condition
Table
3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Table
3.5 Summary
of submission status under FEP-03/356/2009 Condition
Table
3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Table
3.7 Summary
of submission status under FEP-04/356/2009 Condition
Table 3.9 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2012/08
Table 3.10 Summary of submission status under
EP-356/2009 & FEP-06/356/2009 Condition
Table 3.11 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2010/08
Table 3.12 Summary of submission status under EP-356/2009
and FEP-07/356/2009 Condition
Table
4.1 Noise
Monitoring Station
Table 4.2 Air Monitoring Station
Table 4.3 Marine Water Quality Stations for
Water Quality Monitoring
Table 4.4 Marine Water Quality Monitoring
Frequency and Parameters
Table 4.5 Marine Water Quality Stations for
Enhanced Water Quality Monitoring
Table 5.1
Noise
Monitoring Station for Contract no. HK/2009/02
Table 5.2
Noise
Monitoring Station for Contract no. HY/2009/15
Table 5.4 Noise Monitoring Station for Contract no.
HY/2010/08
Table 5.6
Air
Monitoring Station for Contract no. HK/2009/02
Table 5.7
Air
Monitoring Station for Contract no. HY/2009/15
Table 5.9 Air Monitoring
Stations for Contract no. HK/2012/08
Table 5.10 Air Monitoring
Stations for Contract no. HY/2010/08
Table
5.13 Water
quality monitoringStations for Contract no. HK/2009/02
Table 5.14 Water quality monitoringStations for Contract
no. HK/2012/08
Table 5.15 Water quality monitoring Station for Contract no. HY/2010/08
Table 5.16 Enhance Dissolved Oxygen Monitoring Stations for Contract no.
HY/2010/08
Table 5.18 Details of Waste Disposal for Contract no. HK/2009/02
Table 5.19 Details
of Waste Disposal for Contract no. HY/2009/15
Table 5.21 Details of Waste
Disposal for Contract no. HK/2012/08
Table 5.22 Details of Waste
Disposal for Contract no. HY/2010/08
Table 8.2 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.3 Summary of Environmental Inspections for
Contract no. HK/2012/08
Table
9.1 Cumulative
Statistics on Complaints
Table
9.2 Cumulative
Statistics on Successful Prosecutions
Table
10.1 Construction
Activities and Recommended Mitigation Measures in Coming Reporting Month
lIST
OF FIGUREs
Figure 2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST
OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical Presentations
Appendix 5.4 Water Quality Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Summary for Notification of Exceedance
Appendix 10.1 Construction Programme of Individual Contracts
EXECUTIVE SUMMARY
i.
This is the
Environmental Monitoring and Audit (EM&A) Monthly Report
– March 2020 for the Project of Wan Chai Development Phase II and
Central-Wanchai Bypass under Environmental Permit no. EP-356/2009 and Further
Environmental permit nos. FEP-03/356/2009, FEP-04/356/2009 and EP-07/356/2009.
This
report presents the environmental monitoring findings and information recorded
during the period of 27 February 2020 to 26 March 2020. The cut-off date
of reporting is at 26th of each reporting month.
ii.
In the reporting
month, the principal work activities of individual contracts conducted are as follow:
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East
Nil
Contract no. HY/2009/15- Wan Chai Bypass Tunnel (Causeway Bay Typhoon
Shelter Section)
Nil
Contract no. HY/2010/08- Wan Chai Bypass Tunnel (Slip Road 8)
Nil
Noise
Monitoring
iii.
No action
or limit level exceedance was recorded in the reporting period.
iv.
With respect to the shift in major construction
site portions at Wan Chai North, the noise monitoring station M1a – Harbour Sports
Centre was finely adjusted from East of Harbour Road Sports Centre to West of
Harbour Road Sports Centre on 21 June 2016.
v.
With respect to the
demolition of Ex-Harbour Road Sports Centre, the respective noise monitoring
station M1a – Harbour Road Sports Centre were finely adjusted on 16 and 25 May
2017 and thereafter to the Footbridge for Harbour Road Sports for noise
monitoring.
vi.
As
confirmed by CWB RSS, the marine construction works under Contract HY/2010/08
and relevant reporting have been completed by 21 September 2018, the noise
monitoring station namely M2b – Noon day gun area and M3a - Tung Lo Wan Fire
Station association with Contract HY/2010/08 and relevant reporting has been
ceased in the reporting month.
vii.
As
confirmed by WDII RSS, the marine construction works under HK/2012/08 and
relevant reporting have been completed by 2 January 2019, the noise monitoring
station namely M1a - Footbridge for Ex-Harbour Road Sports Centre association
with Contract HK/2012/08 and relevant reporting has been ceased in the
reporting month.
viii.
As
confirmed by CWB RSS, the seabed reinstatement works was resumed under Contract
HY/2009/15 at EX-PCWA area on 26 June 2019 and the relevant noise monitoring
station monitoring station namely M2b – Noon day gun area and M3a - Tung Lo Wan
Fire Station would be associated with Contract HY/2009/15 in the reporting
month.
ix.
As
confirmed by CWB RSS, the marine construction works under Contract HY/2009/19
and relevant reporting have been completed, the monitoring association with
Contract HY/2009/19 namely M4b – Victoria Centre, M5b – City Garden and
M6 –HK Baptist Church Henrietta Secondary School and relevant reporting has been ceased in the reporting month.
x.
As confirmed by CWB RSS, the seabed
reinstatement works was resumed under Contract HY/2010/08 at CBTS area on 7
August 2019 and the relevant noise monitoring station monitoring station namely
M2b – Noon day gun area and M3a - Tung Lo Wan Fire Station would be associated
with Contract HY/2010/08 in the reporting month.
xi.
Referring to WDII RSS confirmation on the
completion of marine works under HK/2009/02 within the EP-356 area on 30
September 2019, the relevant noise monitoring station namely M1a – Footbridge
for Ex-Harbour Road Sports Centre would not be
associated with Contract HK/2009/02 in the reporting month.
xii.
Noise
monitoring during daytime hour were conducted at the stations M2b and M3a on a
weekly basis in the reporting month.
Air
Quality Monitoring
xiii.
No action
or limit level exceedance was recorded in the reporting period.
xiv.
With respect
to the proposed demolition of the Oil Street Site Office, the respective air
quality monitoring station CMA1b – Oil Street Site Office was finely adjusted
from the Oil Street Site Office to Harbour Grand Hotel Boundary Wall from 05
June 2017 onwards.
xv.
With respect to the
proposed demolition of eastern podium of Oil Street Site Office, the respective
air quality monitoring station CMA1b – Oil Street Site Office was finely
adjusted from East podium of the Oil Street Site Office to the West podium of
the Oil Street Site Office on 21 December 2016.
xvi.
As
confirmed by CWB RSS, the marine construction works under Contract HY/2010/08
and relevant reporting have been completed by 21 September 2018, the air
monitoring stations namely CMA3a - CWB PRE Site Office association with Contract
HY/2010/08 and relevant reporting has been ceased in the reporting month.
xvii.
As
confirmed by WDII RSS, the marine construction works under HK/2012/08 and
relevant reporting have been completed by 2 January 2019, the air monitoring
stations namely CMA5b - Pedestrian Plaza, CMA6a – WDII PRE Office association
with Contract HK/2012/08 and relevant reporting has been ceased in the
reporting month.
xviii.
As
confirmed by CWB RSS, the seabed reinstatement works was resumed under Contract
HY/2009/15 at EX-PCWA area on 26 June 2019 and the relevant air monitoring
station monitoring station namely CMA3a – CWB PRE Site Office would be
associated with Contract HY/2009/15 in the reporting month.
xix.
As
confirmed by CWB RSS, the marine construction works under Contract HY/2009/19
and relevant reporting have been completed, the monitoring association with
Contract HY/2009/19 namely CMA1b – Harbour
Grand Hotel Boundary Wall and CMA2a Causeway Bay Community Centre and relevant reporting has been ceased
in June 2019 reporting month.
xx.
As
confirmed by CWB RSS, the seabed reinstatement works was resumed under Contract
HY/2010/08 at CBTS area on 7 August 2019 and the relevant air monitoring
station monitoring station namely CMA3a – CWB PRE Site Office would be
associated with Contract HY/2010/08 in the reporting month.
xxi.
Referring
to WDII RSS confirmation on the completion of marine works under HK/2009/02
within the EP-356 area on 30 September 2019, the relevant air quality
monitoring stations namely CMA3a – CWB PRE Site Office and CMA4a - SPCA would
not be associated with Contract HK/2009/02 in the reporting month.
xxii.
1-hour
and 24-hour Total Suspended Particulates (TSP) monitoring were conducted at
CMA3a – CWB PRE Site Office Area in the reporting month.
Water
Quality Monitoring
xxiv.
With
respect to the reinstatement of the silt screen system for Cooling Water
Intakes P7, P8, P9 and WSD Water Intake RW21, the respective water
quality monitoring was reverted to the previous monitoring location for Water
Quality Monitoring Station RW21-P789 from water quality stations RW21-P789 East
(RW21-P789E) and RW21-P789 West (RW21-P789W) from 25 January 2017 onwards.
xxv.
With respect to the removal
of silt screen at WQM station RW21-P789 on 26 November 2016, the respective
water quality monitoring at RW21-P789 was adjusted to RW21-P789E and RW21-P789W
since 28 November 2016 ebb-tide.
xxvi.
With respect to the
temporarily suspension of marine construction works at WCR3 Area by Contract
HK/2009/02, the installed silt screen for intake group (P7, P8, P9 and WSD21)
was removed on 26 November 2016.
xxvii.
As advised by the
Contractor of HK/2009/01, all silt screen remains removal works at P1, P3, P4,
P5 and C1 water quality monitoring stations were completed on 8 May 2016.
xxviii.
With
respect to the marine works undertaken at WCR3 by Contract HK/2009/02, the
respective water quality monitoring station C1 associated with Contract
HK/2009/01 was updated as in association with Contract HK/2009/01 and Contract
HK/2009/02.
xxix.
With
respect to the marine works undertaken at CBTS by Contract HY/2010/08, the
respective water quality monitoring station C7 associated with Contract
HY/2009/15 was updated as in association with Contract HY/2009/15 and Contract
HY/2010/08.
xxx.
With
respect to the marine works undertaken at HKCEC2 by Contract HK/2012/08, the
respective water quality monitoring station WSD19, P1, P3, P4, and P5 were
associated with Contract HK/2012/08.
xxxi.
As
confirmed by WDII RSS, the marine construction works under Contract HK/2009/01
have been completed since 24 July 2017, the monitoring association with
Contract HK/2009/01 and relevant reporting has been ceased in the reporting
month.
xxxii.
Enhanced DO monitoring at Windsor House
Cooling (Station Ref: C7) was temporarily suspended since 22 October 2014 with respect
to the formation of temporary reclamation zone TS3
xxxiii.
Referring to CWB RSS confirmation on the
completion of marine construction activities within the Ex-PCWA
area and the completion of the post construction water quality monitoring, the respective
Enhance DO Monitoring within Ex-PCWA for monitoring station Ex-PCWA SE and Ex-PCWA SW was
temporarily suspended since 07 March 2017 ebb tide onwards.
xxxiv.
Water quality monitoring station C7 and Enhance
DO monitoring station C6 shall be associated with Contract HY/2010/08, upon confirmation of marine
construction works completion under Contract HY/2009/15 at CBTS area and Ex-PCWA area since
19 June 2017.
xxxv.
Enhanced DO monitoring at Windsor House Cooling
(Station Ref: C7) was resumed from 1 February 2018 onwards with respect to the
completion of removal of temporary reclamation zone.
xxxvi.
Referring to CWB RSS confirmation on the
completion of removal of temporary reclamation within the TS3 area
and the completion of the post construction water quality monitoring, the
respective Enhance DO Monitoring within TS3 for monitoring station C6 and C7
was temporarily suspended since 05 March 2018 onwards.
xxxvii.
Referring to CWB RSS confirmation on the
completion of marine works within the TS3 area and the completion of the post construction water quality
monitoring, the respective water quality monitoring within TS3 for monitoring
station C7 was temporarily suspended since 29 October 2018 onwards.
xxxviii.
Referring to WDII RSS confirmation on the
completion of marine works under HK/2012/08 within the EP-356 area
on 2 January 2019 and the completion of the post construction water quality
monitoring (From 2 January 2019 to 30 January 2019), the respective water
quality monitoring stations P1, P3, P4, P5 and WSD19 within EP-356 area was temporarily
suspended since 15 February 2019 onwards.
xxxix.
Referring to CWB RSS confirmation on the
resumption of marine works within the CBTS area the respective water quality monitoring within CBTS for
monitoring station C7 was resumed since 7 August 2019 and associated with
Contract HY/2009/15 and HY/2010/08.
xl.
Referring
to WDII RSS confirmation on the completion of marine works under HK/2009/02 within
the EP-356 area on 30 September 2019 and the completion of the post
construction water quality monitoring (From 30 September 2019 to 26 October 219),
the respective water quality monitoring stations C1 and RW21-P789 within EP-356
area was temporarily suspended from 26 October 2019 onwards.
xli.
One
action level exceedance of Turbidity during ebb tide on 11 March 2020 was
recorded in this reporting month. After investigation, the exceedance was not
related to Project.
xlii.
Three
limit level exceedance of Turbidity during flood tide on 9 March 2020 and
during both flood and ebb tide on 13 March 2020 were recorded. After
investigation, the exceedances were not related to Project.
Table I Summary
of Water Quality Monitoring Exceedances in Reporting Month
Water
quality monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
HY/2010/08
& HY/2009/15 |
C7 |
0 |
0 |
0 |
2 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
Total |
0 |
0 |
0 |
2 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
1. The cessation of seawater intake
operation for C6 was confirmed on 17 May 2011 and the water quality monitoring
at C6 was then terminated since 17 May 2011.
2. 4-week post construction water quality
monitoring at WSD9, WSD10, WSD15 and WSD17 were completed on 6 Feb 2012 and the
water quality monitoring at WSD 10 and WSD15 were temporary suspended since 8
Feb 2012, and WSD9 and WSD17 was implemented with respect to HK/2009/02 from 8
Feb 2012 onwards.
3. C8 and C9 were implemented with
respect to HY/2009/19 from 28 Jan 2012.
4. C8 & C9 were temporary suspended
since 4 March 2013.
5. WSD7 and WSD20 water quality monitoring
were temporarily suspended from 27 Apr 2012.
6. C2, C3 C4e and C4w water quality
monitoring station was temporarily suspended since 22 Apr 2013
7. P1, P3, P4 and P5 were commenced since
24 Apr 2013
8. C5e and C5w water quality monitoring
station was temporarily suspended since 29 Jul 2013.
9. WSD21 water quality monitoring station
was temporarily suspended since 12 Mar 2014
10. WSD9 and WSD17 water quality
monitoring station was temporarily suspended since 8 Sep 2014 flood tide.
11. The water quality monitoring station
C1 shall be associated with Contract No. HK/2009/02 upon commencement of marine
works under DP3 at WCR3 area.
12. The water quality monitoring station
RW21-P789 was adjusted to RW21-P789E and RW21-P789W since 28 November 2016
ebb-tide.
13. The water quality monitoring was
reverted to previous monitoring station RW21-P789 from PW21-P789E and
RW21-P789W from 25 January 2017 onwards.
14.
Referring
to WDII RSS confirmation on the completion of marine works under HK/2009/02
within the EP-356 area on 30 September 2019 and the completion of the post
construction water quality monitoring (From 30 September 2019 to 26 October
219), the respective water quality monitoring stations C1 and RW21-P789 within
EP-356 area was temporarily suspended from 26 October 2019 onwards.
Complaints,
Notifications of Summons and Successful Prosecutions
xliii.
A public
complaint made to EPD on 18 December 2019 was received by ET on 12 March 2020.
The complainant reported that oil slick was spotted on sea surface outside Expo
Drive East next to the Hong Kong Convention and Exhibition Centre on 18
December 2019.
ET confirmed with the Resident Site
Staff that no construction activity was undertaken around the concerned
location under Contract HK/2009/02 on 18 December 2019 and the coastline of the
concerned area has already been handed over to other party.
Site
Inspections and Audit
xliv.
The Environmental
Team (ET) conducted weekly site inspections for Contract nos. HK/2009/02, HY/2009/15 and HY/2010/08 under EP no. EP-356/2009
in the reporting month. Major observations and recommendations made during the
audit sessions were rectified by the Contractors. No non-conformance was
identified during the site inspections.
Future Key Issues
xlv.
In coming reporting
month, the principal work activities of individual contracts are anticipated as
follows:
Contract no. HK/2009/02 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Wan Chai East
Nil
Contract
no. HY/2009/15- Wan Chai Bypass Tunnel (Causeway Bay Typhoon Shelter Section)
Nil
Contract
no. HY/2010/08- Wan Chai Bypass Tunnel (Slip Road 8 Section)
Nil
1.1.1. Lam Geotechnics Limited (LGL) has
been appointed to work as the Environmental Team (ET) under Environmental
Permit no. EP-356/2009 and Further Environmental permit nos. FEP-03/356/2009,
FEP-04/356/2009 and FEP-07/356/2009 to implement the Environmental Monitoring
and Audit (EM&A) programme as stipulated in the EM&A Manual of the
approved Environmental Impact Assessment (EIA) Report for Wan Chai Development
phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the
EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-041/2001).
1.1.2. This report presents the
environmental monitoring and auditing work carried out in accordance to the
Section 10.3 of EM&A Manual and “Environmental Monitoring and Audit
Requirements” under Particular Specification Section 27.
1.1.3. This report documents the finding
of EM&A works for Environmental Permit no. EP-356/2009, Further
Environmental Permit no. FEP-03/356/2009, FEP-04/356/2009 and FEP-07/356/2009 during
the period of 27 February 2020 to 26 March 2020.
The cut-off date of reporting is at 26th of each reporting month.
Section
1 Introduction –
details the scope and structure of the report.
Section
2 Project Background –
summarizes background and scope of the project, site description, project
organization and contact details of key personnel during the reporting period.
Section
3 Status of Regulatory Compliance –
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring Requirements –
summarizes all monitoring parameters, monitoring methodology and equipment,
monitoring locations, monitoring frequency, criteria and respective event and
action plan and monitoring programmes.
Section
5 Monitoring Results –
summarizes the monitoring results obtained in the reporting period.
Section
6 Compliance Audit – summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due
to the Concurrent Projects – summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Environmental Site Audit –
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a
review of any
relevant follow-up actions
within the reporting period.
Section
9 Complaints, Notification of
summons and Prosecution – summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1. “Wan Chai Development phase II and
Central-Wan Chai Bypass” and “Central-Wan Chai Bypass and Island Eastern
Corridor Link” (hereafter called “the Project”) are Designed Project (DP) under
the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai
Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
have been approved on 31 August 2001 and 11 December 2008 respectively.
2.1.2. The key purpose of Wan Chai
Development Phase II (WDII) is to provide land at Wan Chai North and North
Point for construction of the Central-Wan Chai Bypass and Island Eastern
Corridor Link (CWB). Land formed under the project will be developed as a
world-class waterfront promenade joining that at the new Central waterfront for
public enjoyment.
2.1.3. There is a compelling and present
need for the CWB to provide relief to the very congested east-west Connaught
Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is
currently operating beyond its capacity. The CWB will provide relief to the
existing congestion along the Corridor and cater for the anticipated growth of
traffic on Hong Kong Island. Without the CWB and its access roads, there will
not be sufficient capacity to serve the heavy traffic demands at both strategic
and local levels.
2.2.1. The Project is located mainly in
Wan Chai North, Causeway Bay and North Point, and is demarcated by Gloucester
Road and Victoria Park Road to the south, Fenwick Pier Street to the west and
Tong Shui Road Interchange to the east, as shown in Figure 2.1.
2.2.2. The study area encompasses
existing developments along the Wan Chai, Causeway Bay and North Point
shorelines. Major land uses include the Hong Kong Convention & Exhibition
Centre (HKCEC) Extension, the Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo
Working Area (ex-PCWA), the Royal Hong Kong Yacht Club (RHKYC), the Police
Officers’ Club, the Causeway Bay Typhoon Shelter (CBTS) and commercial and
residential developments.
2.2.3.
The scope of the Project comprises:
·
Land formation for
key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for
connection to the Trunk Road and for
through traffic from Central to Wan Chai and Causeway Bay. The land
formed for the above transport
infrastructure will provide opportunities for the development of an attractive
waterfront promenade for the enjoyment of the public
·
Reprovisioning /
protection of the existing facilities and structures affected by the land
formation works mentioned above
·
Extension,
modification, reprovisioning or protection of existing storm water drainage
outfalls, sewerage outfalls and watermains affected by the revised land use and
land formation works mentioned above
·
Upgrading of
hinterland storm water drainage system and sewerage system, which would be
rendered insufficient by the land formation works mentioned above
·
Provision of the
ground level roads, flyovers, footbridges, necessary transport facilities and
the associated utility services
·
Construction of the
new waterfront promenade, landscape works and the associated utility services
·
The Trunk Road
(i.e. CWB) within the study area and the associated slip roads for connection
to the Trunk Road.
2.2.4. The project also contains various
Schedule 2 DPs that, under the EIAO, require Environmental Permits (Eps) to be
granted by the DEP before they may be either constructed or operated. Table
2.1 summarises the five individual DPs under this Project. Figure
2.1
shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2
Designated Projects under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai
Bypass (CWB) including its road tunnel and slip roads |
Schedule 2,
Part I, A.1 and A.7 |
Trunk road
and road tunnel more than 800 m in length |
DP2 |
Road P2 and
other roads which are classified as primary/district distributor roads |
Schedule 2,
Part I, A.1 |
Primary /
district distributor roads |
DP3 |
Reclamation
works including associated dredging works |
Schedule 2,
Part I, C.1 and C.12 |
Reclamation
more than 5 ha in size and a dredging operation less than 100 m from a
seawater intake point |
DP5 |
Wan Chai East
Sewage Outfall |
Schedule 2,
Part I, F.5 and F.6 |
Submarine
sewage pipelines with a total diameter more than 1,200 mm and include a
submarine sewage outfall |
DP6 |
Dredging for
the Cross-harbour Water Mains from Wan Chai to Tsim
Sha Tsui |
Schedule 2,
Part I, C.12 |
A dredging
operation less than 100 m from a seawater intake point |
2.3.1. Due to the multi-contract nature
of the Project, there are a number of contracts sub-dividing the whole works
area into different work areas to be commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits (FEP) such that the impact monitoring stations are sub-divided
accordingly to facilitate the implementation of EM&A programme and to
streamline the EM&A reporting for individual FEP holders correspondingly.
2.3.2. The details of individual
contracts are summarized in Table 2.2.
Table 2.2 Details of Individual
Contracts under the Project
Contract No. |
Contract
Title |
Associated DP(s) |
Construction Commencement
Date |
HK/2009/01 |
Wan Chai
Development Phase II – Central –Wanchai Bypass at Hong Kong Convention and
Exhibition Centre |
DP3, DP6 |
23 July 2010 (Completed) |
DP1, DP2 |
25 August
2011 (Completed) |
||
HK/2009/02 |
Wan Chai
Development Phase II – Central – Wan Chai Bypass at WanChai East |
DP3,
DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development
Phase II and Central – Wan Chai Bypass – North Point Reclamation |
DP3 |
17 March 2010 (Completed) |
HY/2009/15 |
Central-Wanchai
Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) |
DP3 |
10 November
2010 |
DP1 |
13 July 2011
(Completed) |
||
HK/2010/06 |
Wan Chai
Development Phase II-Central-Wan Chai Bypass over MTR Tsuen Wan Line |
DP3 |
22 March 2011 (Completed) |
04/HY/2006 |
Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street |
DP1 |
September 2010 (Completed) |
HY/2009/17 |
Central – Wan
Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central – Wan
Chai Bypass (CWB) – Central Interchange |
DP1 |
21 April 2011 (Completed) |
HY/2009/19 |
Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2012/08 |
Wan Chai Development Phase II Central- Wan Chai Bypass at Wan Chai West |
DP1,DP2, DP3 |
10 March 2014 (Completed) |
HY/2010/08 |
Central-
Wanchai Bypass Tunnel – Tunnel (Slip Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central-Wan
Chai Bypass (CWB) – Tunnel Buildings, Systems and Fittings, and Works
Associated with Tunnel Commissioning |
DP1 |
8 October
2014 |
2.4.1. Civil Engineering and Development
Department and Highways Department are the overall project controllers for the
Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the
construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2. The proposed project organization
and lines of communication with respect to environmental protection works are
shown in Figure 2.2. Key personnel and contact
particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer’s
Representative for WDII |
Resident
Engineer |
Mr.
Eliot Liu |
3519 9167 |
2587 1877 |
Engineer’s
Representative for CWB |
Chief
Resident Engineer |
Mr.
Dennis Norton |
3912 3188 |
3912 3010 |
|
Chun Wo –
CRGL Joint Venture |
Contractor
under Contract no. HK/2009/02 |
Project Manager |
Mr.
Paul Yu |
3658 3085 |
2827 9996 |
Quality &
Environmental Manager |
Mr.
Samuel Chan |
9646
5780 |
|||
China State
Construction Engineering (HK) Ltd. |
Contractor
under Contract no. HY/2009/15 |
Project
Director |
Mr.
Chris Leung |
3557 6393 |
2566 2192 |
Site Agent |
Mr.
Patrick Ho |
3557 6405 |
|||
Construction
Manager |
Mr.
Tom Tong |
3557 6415 |
|||
Environmental
Officer |
Mr. Gabriel Wong |
6114 9590 |
|||
Environmental
Supervisor |
Mr.
Gordon Lai |
6145 6365 |
|||
China State |
Contractor under Contract no. HY/2010/08 |
Project
Director |
Mr. Chris Leung |
3467 4299 |
2566 8061 |
Project
Manager |
Mr. Chan Ying Lun |
3418 3001 |
|||
Site Agent |
Mr. Thomas Lui |
3557 6452 |
|||
Marine
Manager |
Mr. Nickael Chan |
3557 6333 |
|||
Construction
Manager |
Mr. Tom Tong |
3557 6367 |
|||
Environmental
Officer |
Mr. Gabriel Wong |
3557 6466 |
|||
Ramboll Hong Kong Limited |
Independent Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr.
David Yeung |
3465 2888 |
3465 2899 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr.
Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3. In the reporting month, the principal
work activities of individual contracts conducted are as follow:
Contract no. HK/2009/02 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Wan Chai East
Nil
Contract no. HY/2009/15- Wan Chai Bypass
Tunnel (Causeway Bay Typhoon Shelter Section)
Nil
Contract no. HY/2010/08- Wan Chai
Bypass Tunnel (Slip Road 8)
Nil
2.4.4. In coming reporting month, the
principal work activities of individual contracts are anticipated as follows:
Contract no. HK/2009/02 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Wan Chai East
Nil
Contract no. HY/2009/15- Wan Chai
Bypass Tunnel (Causeway Bay Typhoon Shelter Section)
Nil
Contract no. HY/2010/08- Wan Chai
Bypass Tunnel (Slip Road 8)
Nil
3.1.1.
A
summary of the current status on licences and/or permits on environmental
protection pertinent to the Project is shown in Table 3.1.
Table 3.1 Summary
of the current status on licences and/or permits on environmental protection
pertinent to the Project
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Further
Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Surrendered |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Surrendered |
Further Environmental Permit |
FEP-06/356/2009 |
5 Mar 2013 |
Surrendered |
Further Environmental Permit |
FEP-07/356/2009 |
26 July 2013 |
Valid |
Further Environmental Permit |
FEP-08/356/2009 |
1 Aug 2016 |
Surrendered |
Environmental Permit |
EP-364/2009/G |
10 Oct 2019 |
Valid |
Further Environmental Permit |
FEP-01/364/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
Surrendered |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
Surrendered |
Further Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
Surrendered |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Surrendered |
Further Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-07/364/2009/G |
10 Oct 2019 |
Valid |
Further Environmental Permit |
FEP-08/364/2009/A |
15 Jun 2012 |
Surrendered |
Further Environmental Permit |
FEP-09/364/2009/B |
5
March 2013 |
Valid |
Further Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
Further Environmental Permit |
FEP-11/364/2009/E |
22 Dec 2016 |
Valid |
Further Environmental Permit |
FEP-12/364/2009/D |
1 Aug 2016 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2009 |
Valid |
Further Environmental Permit |
FEP-01/376/2009 |
31 Mar 2015 |
Valid |
Further Environmental Permit |
FEP-02/376/2009 |
1 Aug 2016 |
Valid |
3.1.2.
Due
to the multi-contract nature of the Project, the status of permits and/or
licences under the individual contract(s) are presented as below:
Contract
no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
WanChai East
3.1.3.
Summary of the current status
on licences and/or permits on environmental protection pertinent and submission
for contract no. HK/2009/02 under FEP-03/356/2009 are shown in Table 3.4 and
Table 3.5.
Table 3.4 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS1072-19 |
28/11/2019 |
30 Nov 2019 to 28 May 2020 |
Valid |
Discharge
Licence |
WT00022295-2015 |
12
Aug 2015 |
31
July 2020 |
Valid |
WT00025276-2016 |
19
Sep 2016 |
31
July 2021 |
Valid |
|
Billing
Account under Waste Disposal Ordinance (Land) |
7010255 |
10
Feb 2010 |
N/A |
Valid |
Billing
Account under Waste Disposal Ordinance (Marine) |
7011496 |
6
Oct 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10
Mar 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22
Sep 2010 |
N/A |
Valid |
Table 3.5 Summary of submission status under
FEP-03/356/2009 Condition
EP
Condition |
Submission |
Date of Submission |
Condition 1.12 |
Commencement Date of Construction of Marine Works |
8 April 2010 |
Condition 2.6 |
Management Organization of Main Construction
Companies |
10 April 2010 |
Condition 2.7 |
Works Schedule and Location Plans |
8 April 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan (Revision A) |
20 April 2010 |
Silt Curtain Deployment Plan (Revision B) |
25 May 2010 |
|
Silt Curtain Deployment Plan (Revision C) |
14 Jun 2010 |
|
Silt Curtain Deployment Plan (Revision H) |
15 Feb 2011 |
|
Silt Curtain Deployment Plan (Revision I) |
17 Nov 2011 |
|
Silt Curtain Deployment Plan (Revision J) |
15 Feb 2012 |
|
Silt Curtain Deployment Plan (Revision K) |
3 May 2012 |
|
Silt Curtain Deployment Plan (Revision L) |
25 Oct 2012 |
|
Silt Curtain Deployment Plan (Revision M) |
30 Nov 2012 |
|
Silt Curtain Deployment Plan (Revision N) |
11 Apr 2018 |
|
Silt Curtain Deployment Plan (Revision O) |
24 May 2018 |
|
Silt Curtain Deployment Plan (Revision P) |
30 July 2019 |
|
Condition 2.9 |
Silt Screen Deployment Plan |
21 April 2010 |
Supplementary Information for Existing WSD Salt
Water Intakes at Quarry Bay and Sai Wan Ho |
5 Oct 2010 |
|
Silt Screen Deployment Plan (Revision B) |
15 Feb 2012 |
|
Silt Screen Deployment Plan (Revision C) |
3 May 2012 |
|
|
Silt Screen Deployment Plan (Revision D) |
10 Dec 2012 |
|
Silt Screen Deployment Plan (Revision E) |
6 May 2013 |
|
Silt Screen Deployment Plan (Revision F) |
23 Nov 2016 |
Condition 2.17 |
Noise Management Plan |
6 May 2010 |
Condition 2.18 |
Landscape Plan (Decorative Screen Hoarding) |
11 May 2010 |
Landscape Plan (Control of Night Time Lighting) |
2 June 2010 |
|
Landscape Plan (Combined Version) |
20 July 2011 |
|
Landscape Plan (Combined Version) |
5 Aug 2011 |
|
----- |
Acknowledge of Submission |
22 Aug 2011 |
----- |
Form 7: Surrender of Environmental
Permit |
26 March 2020 |
Contract
no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section)
3.1.4.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and submission for contract no. HY/2009/15 under FEP-04/356/2009 are
shown in Table 3.6 and Table 3.7.
Table 3.6 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/15
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Registration
as a Chemical Waste Producer |
WPN5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7011553 |
30 Sep 2010 |
N/A |
Valid |
Table 3.7 Summary of submission status under
FEP-04/356/2009 Condition
FEP Condition |
Submission |
Date of Submission |
Condition
2.6 |
Management
Organization of Main Construction Companies |
30
Sep 2010 |
Amendment
for Management Organization of Main Construction Companies |
16 May 2011 |
|
Condition 2.7 |
Works Schedule and Location Plans |
27 Oct 2010 |
|
Amendment for Works Schedule and
Location Plans |
12 Nov 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan |
30 Nov 2010 |
Amendment for Silt Curtain Deployment
Plan |
24 Feb 2011 |
|
Amendment for Silt Curtain Deployment
Plan |
11 May 2011 |
|
Amendment for Silt Curtain Deployment
Plan |
11 Sep 2012 |
|
Amendment for Silt Curtain Deployment
Plan |
30 Oct 2012 |
|
Silt Curtain Deployment Plan (Rev.7) |
16 Dec 2019 |
|
Condition 2.9 |
Silt
Screen Deployment Plan |
19 Oct 2010 |
Amendment for Silt Screen Deployment
Plan |
18 Feb 2011 |
|
Amendment for Silt Screen Deployment
Plan |
15 Jun 2011 |
|
Silt Screen Deployment Plan (Rev. 4) |
26 Nov 2019 |
|
Condition 2.18 |
Proposal
for the Removal of Odorous Sediment and Slime |
13 Jan 2011 |
Amendment for Proposal for the Removal
of Odorous Sediment and Slime |
8 Mar 2011 |
|
Amendment for Proposal for the Removal
of Odorous Sediment and Slime |
2 Aug 2011 |
|
Condition 2.21 |
Landscape Plan |
18 Feb 2011 |
Condition 2.23 |
Noise Management Plan |
20 Oct 2010 |
Amendment for Noise Management Plan |
27 Jan 2011 |
Contract no. HY/2010/08 –Central - Wan Chai Bypass
(CWB) –Tunnel (Slip Road 8)
3.1.5. Summary of the current status on
licences and/or permits on environmental protection pertinent and submission
for contract no. HY/2010/08 under FEP-07/356/2009 are shown in Table 3.11
and Table
3.12.
Table 3.11
Cumulative Summary of Valid Licences and Permits under Contract no. HY/2010/08
Permits
and/or Licences |
Reference
No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-07/356/2009 |
26 Jul 2013 |
NA |
Valid |
FEP-10/364/2009/B |
26 Jul 2013 |
NA |
Valid |
|
Notification
of Works Under APCO |
357176 |
2 Apr 2013 |
N/A |
Valid |
Registration
as a Chemical Waste Producer |
WPN5213-147-C1169-44 |
27 Mar 2013 |
N/A |
Valid |
Billing
Account under Waste Disposal Ordinance |
7017170 |
27 Mar 2013 |
N/A |
Valid |
Billing Account under Waste Disposal
Ordinance (Dumping by Vessel) |
7020947 |
22 Dec 2014 |
N/A |
Valid. |
Construction
Noise Permit |
GW-RS1115-19 |
16 Dec 2019 |
3 Jan 2020
to 1 Jul 2020 |
Valid |
Table 3.12 Summary of submission status under EP-356/2009 and FEP-07/356/2009 Condition
FEP Condition |
Submission |
Date of Submission |
Condition 2.8 |
Silt Curtain
Deployment Plan (Rev 6) |
16 Dec 2019 |
Condition
2.9 |
Silt
Screen Deployment Plan (Rev 5) |
1
March 2019 |
Condition
2.23 |
Noise
Management Plan (Rev 2) |
25 Mar 2014 |
Condition
2.24 |
Landscape
Plant (Rev 2) |
23 Sep 2014 |
Noise Monitoring Stations
4.1.1.
The
noise monitoring stations for the Project are listed and shown in Table
4.1 and Figure
4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.1 Noise Monitoring Station
Station |
Description |
M1a |
Footbridge for Ex-Harbour Road Sports Centre* |
M2b |
Noon
Gun Area |
M3a |
Tung
Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK
Baptist Church Henrietta Secondary School |
Remarks*: With respect to the demolition of
Ex-Harbour Road Sports Centre, the respective noise monitoring station M1a –
Harbour Road Sports Centre were finely adjusted on 16 and 25 May 2017 and
thereafter to the Footbridge for Harbour Road Sports for noise monitoring
Noise Monitoring Parameters, Frequency and Duration
4.1.2.
The construction noise level shall be measured in terms of the
A-weighted equivalent continuous sound pressure level (Leq).
Leq (30 minutes) shall be used
as the monitoring parameter for the time period between 0700 and 1900 hours on
normal weekdays. For all other time periods, Leq
(5 minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria. Supplementary information for data auditing, statistical results such
as L10 and L90 shall also be obtained for reference.
4.1.3.
Noise
monitoring shall be carried out at all the designated monitoring stations. The
monitoring frequency shall depend on the scale of the construction activities.
The following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
·
One set of
measurements between 0700 and 1900 hours on normal weekdays.
4.1.4.
If
construction works are extended to include works during the hours of 1900 –
0700 as well as public holidays and Sundays, additional weekly impact
monitoring shall be carried out during respective restricted hours periods.
Applicable permits under NCO shall be obtained by the Contractor.
Monitoring Equipment
4.1.5.
As
referred to in the Technical Memorandum ™ issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
4.1.6.
Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
Air Quality Monitoring Stations
4.2.1.
The
air monitoring stations for the Project are listed and shown in Table 4.2
and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.2 Air Monitoring Station
Station ID |
Monitoring
Location |
Description |
CMA1b |
Harbour
Grand Hotel Boundary Wall** |
North Point |
CMA2a |
Causeway
Bay Community Centre |
Causeway Bay |
CMA3a |
CWB PRE Site Office * |
Causeway Bay |
CMA4a |
Society
for the Prevention of Cruelty to Animals |
Wan Chai |
CMA5b |
Pedestrian
Plaza*** |
Wan Chai |
CMA6a |
WDII PRE Site Office * |
Wan Chai |
Remarks*: As per the
ENPC meeting in March 2011, the monitoring stations CMA3a – Future CWB site
office at Wanchai Waterfront Promenade was renamed as remark.
Remarks**: The
location ID of monitoring station CMA1b was updated as “Harbour Grand Hotel
Boundary Wall” from 05 June 2017 onwards.
Remarks***: The
station ID and monitoring location was updated in December 2014 with respect to
monitoring station relocation.
Air Monitoring Parameters, Frequency and Duration
4.2.2.
One-hour
and 24-hour TSP levels should be measured to indicate the impacts of
construction dust on air quality. The 24-hour TSP levels shall be measured by
following the standard high volume sampling method as set out in the Title 40
of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.
4.2.3.
All
relevant data including temperature, pressure, weather conditions, elapsed-time
meter reading for the start and stop of the sampler, identification and weight
of the filter paper, and any other local atmospheric factors affecting or
affected by site conditions, etc., shall be recorded down in detail.
4.2.4.
For
regular impact monitoring, the sampling frequency of at least once in every
six-days, shall be strictly observed at all the monitoring stations for 24-hour
TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least
three times in every six-days should be undertaken when the highest dust impact
occurs.
Sampling Procedure and Monitoring Equipment
4.2.5.
High
volume samplers (HVSs) in compliance with the following specifications shall be
used for carrying out the 1-hour and 24-hour TSP monitoring:
·
0.6 – 1.7 m3 per
minute adjustable flow range;
·
equipped with a
timing / control device with +/- 5 minutes accuracy for 24 hours operation;
·
installed with
elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
capable of providing
a minimum exposed area of 406 cm2;
·
flow control
accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
equipped with a
shelter to protect the filter and sampler;
·
incorporated with an
electronic mass flow rate controller or other equivalent devices;
·
equipped with a flow
recorder for continuous monitoring;
·
provided with a
peaked roof inlet;
·
incorporated with a
manometer;
·
able to hold and
seal the filter paper to the sampler housing at horizontal position;
·
easily changeable
filter; and
·
capable of
operating continuously for a 24-hour period.
4.2.6.
Initial
calibration of dust monitoring equipment shall be conducted upon installation
and thereafter at bi-monthly intervals. The transfer standard shall be
traceable to the internationally recognized primary standard and be calibrated
annually. The concern parties such as IEC shall properly document the
calibration data for future reference. All the data should be converted into
standard temperature and pressure condition.
Laboratory Measurement / Analysis
4.2.7.
A
clean laboratory with constant temperature and humidity control, and equipped
with necessary measuring and conditioning instruments to handle the dust
samples collected, shall be available for sample analysis, and equipment
calibration and maintenance. The laboratory should be HOKLAS accredited.
4.2.8.
An alternative non-HOKLAS accredited laboratory was set-up for carrying out the laboratory analysis,
the laboratory equipment was
approved by the ER on 8 February 2011 and the measurement procedures were witnessed by the IEC. Any measurement performed by the
laboratory was be
demonstrated to the satisfaction of the ER and IEC. IEC shall regularly audit
to the measurement performed by the laboratory to ensure the accuracy of
measurement results.
4.2.9.
Filter
paper of size 8” x 10” shall be labelled before sampling. It shall be a clean
filter paper with no pinholes, and shall be conditioned in a
humidity-controlled chamber for over 24-hours and be pre-weighed before use for
the sampling.
4.2.10.
After
sampling, the filter paper loaded with dust shall be kept in a clean and
tightly sealed plastic bag. The filter paper shall then be returned to the
laboratory for reconditioning in the humidity controlled chamber followed by
accurate weighing by an electronic balance with readout down to 0.1 mg. The
balance shall be regularly calibrated against a traceable standard.
4.2.11.
All
the collected samples shall be kept in a good condition for 6 months before
disposal.
impact monitoring for odour patrol
4.2.12.
Odour
patrols along the shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai
Public Cargo Working Area when there is temporary reclamation in Causeway Bay
Typhoon Shelter and/or in the ex-Wan Chai Public Cargo Working Area, or when
there is dredging of the odorous sediment and slime at the south-western corner
of the Causeway Bay Typhoon Shelter. Odour patrols will be carried out at
bi-weekly intervals during July, August and September by a qualified person of
the ET who shall:
·
be at least 16 years
of age;
·
be free from any
respiratory illnesses; and
·
not be allowed to
smoke, eat, drink (except water) or use chewing gum or sweets 30 min
·
before and during
odour patrol
4.2.13.
Odour
patrol shall be conducted by independent trained personnel / competent persons
patrolling and sniffing around the shore as shown in Figure 4.1 to detect any
odour at the concerned hours (afternoon is preferred for higher daily
temperature).
4.2.14.
The
qualified person will use the nose (olfactory sensor) to sniff odours at
different locations. The main odour emission sources and the areas to be
affected by the odour nuisance will be identified.
4.2.15.
The
perceived odour intensity is to be divided into 5 levels which are ranked in
the descending order as follows:
·
0 – Not detected. No
odour perceived or an odour so weak that it cannot be easily characterized or
described;
·
1 – Slight
Identifiable odour, and slight chance to have odour nuisance;
·
2 – Moderate
Identifiable odour, and moderate chance to have odour nuisance;
·
3 – Strong
Identifiable, likely to have odour nuisance;
·
4 – Extreme Severe
odour, and unacceptable odour level.
4.2.16.
The
findings including odour intensity, odour nature and possible odour sources,
and also the local wind speed and direction at each location will be recorded.
In addition, some relevant meteorological and tidal data such as daily average
temperature, and daily average humidity, on that surveyed day will be obtained
from the Hong Kong Observatory Station for reference. The Action and Limit
levels for odour patrol are shown in Appendix 4.1.
4.2.17.
The
qualified odour patrol member has individual n-butanol thresholds complied with
the requirement of European Standard Method of Air Quality – Determination of
Odour Concentration by Dynamic Olfactometry (EN13725) in the range of 20 to 80
ppb.
4.3.1.
The
EIA Report has identified that the key water quality impact would be associated
with the dredging works during the construction phase. Marine water quality
monitoring for dissolved oxygen (DO), suspended solid (SS) and turbidity is
therefore recommended to be carried out at selected WSD flushing water intakes.
The impact monitoring should be carried out during the proposed dredging works
to ensure the compliance with the water quality standards.
4.3.2.
The
updated EM&A Manual for EP-356/2009 (Version in March 2011) is approval by
EPD on 29 April 2011. As such, the Action Level and Limit Level for the wet
season (April – September) will be effected and applied to the water quality
monitoring data from 30 April 2011.
Water
Quality Monitoring Stations
4.3.3.
Water
quality monitoring was undertaken at 8 monitoring stations for WSD salt water
intakes and cooling water intakes along the seafront of the Victoria Harbour in
the reporting month. The proposed water quality monitoring stations of the
Project are shown in Table 4.3 and Figure 4.1. Appendix
4.1 shows the established Action/Limit Levels for the monitoring
works.
Table 4.3 Marine Water Quality
Stations for Water Quality Monitoring
Station
Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD19 |
Sheung
Wan |
833415.0 |
816771.0 |
Cooling Water Intake |
|||
C1 |
HKCEC
Extension |
835885.6 |
816223.0 |
C7 |
Windsor
House |
837193.7 |
816150.0 |
P1 |
HKCEC
Phase I |
835774.7 |
816179.4 |
P3 |
The Academy of performing Arts |
835824.6 |
816212.0 |
P4 |
Shui on Centre |
835865.6 |
816220.0 |
P5 |
Government Buildings (Wanchai Tower / Revenue
Tower / Immigration Tower) |
835895.2 |
816215.2 |
Cooling Water
Intake / WSD Salt Water Intake |
|||
RW21-P789 |
Great Eagle Centre/ Sun Hung Kai Centre/ WSD Wanchai salt water intake / China Resources
Building |
836268.0 |
816020.0 |
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011 and the water quality monitoring at C6 was then terminated since 17 May 2011.
- 4-week post construction water quality monitoring at WSD9, WSD10, WSD15 and WSD17 were completed on 6 Feb 2012 and the water quality monitoring at WSD 10 and WSD15 were temporary suspended since 8 Feb 2012, and WSD9 and WSD17 was implemented with respect to HK/2009/02 from 8 Feb 2012 onwards.
- C8 and C9
were implemented with respect to HY/2009/19 from 28 Jan 2012.
- C8
& C9 were temporary suspended since 4 March 2013.
- WSD7 and
WSD20 water quality monitoring were temporarily suspended from 27 Apr 2012.
- C2, C3
C4e and C4w water quality monitoring station was temporarily suspended since 22
Apr 2013
- P1, P3,
P4 and P5 were commenced since 24 Apr 2013
- C5e
and C5w water quality monitoring station was temporarily suspended since 29 Jul
2013.
- WSD21
water quality monitoring station was temporarily suspended since 12 Mar 2014
- WSD9
and WSD17 water quality monitoring station was temporarily suspended since 8
Sep 2014 flood tide.
- The water quality monitoring station C1 shall be associated with Contract No. HK/2009/02 upon commencement of marine works under DP3 at WCR3 area.
- The water
quality monitoring station RW21-P789
was adjusted to RW21-P789E and RW21-P789W since 28 November 2016 ebb-tide.
- The water quality monitoring was reverted
to previous monitoring station RW21-P789 from PW21-P789E and RW21-P789W from 25
January 2017 onwards.
Water Quality Parameters
4.3.4.
Monitoring
of dissolved oxygen (DO), turbidity and suspended solids (SS) shall be carried
out at WSD flushing water intakes and cooling water intakes. DO and Turbidity
are measured in-situ while SS is determined in laboratory.
4.3.5.
In
association with the water quality parameters, other relevant data shall also
be measured, such as monitoring location/position, time, sampling depth, water
temperature, pH, salinity, dissolved oxygen (DO) saturation, weather
conditions, sea conditions, tidal stage, and any special phenomena and work
underway at the construction site etc.
Sampling Procedures and Monitoring Equipment
4.3.6.
The
interval between two sets of monitoring should not be less than 36 hours except
where there are exceedances of Action and/or Limit Levels, in which case the
monitoring frequency will be increased. Table 4.4 shows the
proposed monitoring frequency and water quality parameters. Duplicate in-situ
measurements and water sampling should be carried out in each sampling event.
For selection of tides for in-situ measurement and water sampling, tidal range
of individual flood and ebb tides should be not less than 0.5m.
Table 4.4 Marine Water Quality
Monitoring Frequency and Parameters
Activities |
Monitoring
Frequency1 |
Parameters2 |
During
the 4-week baseline monitoring period |
Three
days per week, at mid-flood and mid-ebb tides |
Turbidity,
Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
During
marine construction works |
Three
days per week, at mid-flood and mid-ebb tides |
Turbidity,
Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
After completion of marine construction works |
Three
days per week, at mid-flood and mid-ebb tides |
Turbidity,
Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
Notes:
1. For
selection of tides for in-situ measurement and water sampling, tidal range of
individual flood and ebb tides should be not less than 0.5m.
2.
Turbidity should be measured in situ whereas SS
should be determined by laboratory.
Dissolved Oxygen and Temperature Measuring
Equipment
4.3.7.
The
instrument should be a portable, weatherproof dissolved oxygen measuring
instrument complete with cable, sensor, comprehensive operation manuals, and
use a DC power source. It should be capable of measuring:
·
a dissolved oxygen
level in the range of 0-20 mg/l and 0-200% saturation
·
a temperature of
0-45 degree Celsius
4.3.8.
It
should have a membrane electrode with automatic temperature compensation
complete with a cable. Sufficient stocks of spare electrodes and cables should
be available for replacement where necessary. (e.g. YSI model 59 meter, YSI
5739 probe, YSI 5795A submersible stirrer with reel and cable or an approved
similar instrument).
4.3.9.
Should
salinity compensation not be build-in in the DO equipment, in-situ salinity
shall be measured to calibrate the DO equipment prior to each DO measurement.
Turbidity Measurement Instrument
4.3.10.
The
instrument should be a portable, weatherproof turbidity-measuring instrument
complete with comprehensive operation manual. The equipment should use a DC
power source. It should have a photoelectric sensor capable of measuring
turbidity between 0‑1000 NTU and be complete with a cable (e.g. Hach model
2100P or an approved similar instrument).
Sampler
4.3.11.
A
water sampler comprises a transparent PVC cylinder, with a capacity of not less
than 2 litres, and can be effectively sealed with latex cups at both ends. The
sampler should have a positive latching system to keep it open and prevent
premature closure until released by a messenger when the sampler is at the
selected water depth (e.g. Kahlsico Water Sampler or an approved similar
instrument).
Sample Container and Storage
4.3.12.
Water
samples for suspended solids measurement should be collected in high-density
polythene bottles, packed in ice (cooled to 4°C without being frozen), and
delivered to ALS Technichem (HK) Pty Ltd. as soon as possible after collection
for analysis.
Water Depth Detector
4.3.13.
A
portable, battery-operated echo sounder shall be used for the determination of
water depth at each designated monitoring station. This unit can either be
handheld or affixed to the bottom of the workboat, if the same vessel is to be
used throughout the monitoring programme.
Salinity
4.3.14.
A
portable salinometer capable of measuring salinity in the range of 0-40 ppt
shall be provided for measuring salinity of the water at each of monitoring
location.
Monitoring Position Equipment
4.3.15.
A
hand-held or boat-fixed type digital Global Positioning System (GPS) with
waypoint bearing indication or other equivalent instrument of similar accuracy
shall be provided and used during monitoring to ensure the monitoring vessel is
at the correct location before taking measurements.
Calibration of In-situ Instruments
4.3.16.
All
in-situ monitoring instrument shall be checked, calibrated and certified by a
laboratory accredited under HOKLAS or equivalent before use, and subsequently
re-calibrated at 3 monthly intervals throughout all stages of the water quality
monitoring. Responses of sensors and electrodes should be checked with
certified standard solutions before each use. Wet bulb calibration for a DO
meter shall be carried out before measurement at each monitoring location.
4.3.17.
For
the on site calibration of field equipment by the ET, the BS 127:1993,
"Guide to Field and on-site test methods for the analysis of waters"
should be observed.
4.3.18.
Sufficient
stocks of spare parts should be maintained for replacements when necessary.
Backup monitoring equipment shall also be made available so that monitoring can
proceed uninterrupted even when some equipment is under maintenance,
calibration, etc.
4.3.19.
Current
calibration certificates of equipments are presented
in Appendix
4.2.
Laboratory Measurement / Analysis
4.3.20.
Analysis
of suspended solids has been carried out in a HOKLAS accredited laboratory, ALS
Technichem (HK) Pty Ltd. Water samples of about 1L shall be collected at the
monitoring stations for carrying out the laboratory SS determination. The SS
determination work shall start within 24 hours after collection of the water
samples. The SS determination shall follow APHA 19ed or equivalent methods
subject to the approval of IEC and EPD.
Enhanced Water Quality Monitoring in the ex-Wan Chai Public Cargo
Working Area and the Causeway Bay Typhoon Shelter
4.3.21.
The
enhanced water quality monitoring and audit programme is to avoid aggravation
of odour nuisance from seawater arising from temporary reclamation in the
ex-Wan Chai Public Cargo Working Area and the Causeway Bay Typhoon Shelter.
4.3.22.
Dissolved
oxygen monitoring at the intakes C6 and C7 in Causeway Bay Typhoon Shelter when
there is temporary reclamation in Causeway Bay Typhoon Shelter and at the
south-western and south-eastern corners of the ex-Wan Chai Public Cargo Working
Area. The proposed water quality monitoring stations of the Project are shown
in Table 4.5 and Figure
4.1.
Table 4.5 Marine Water Quality Stations for Enhanced
Water Quality Monitoring
Station |
Location |
C6 |
Proposed
Exhibition Station / World Trade Centre |
C7 |
Windsor House |
Ex-WPCWA-SW |
South-western
of the ex-Wan Chai Public Cargo Working Area |
Ex-WPCWA-SE |
South-eastern
of the ex-Wan Chai Public Cargo Working Area |
Remarks:
1. Enhanced DO monitoring at
Windsor House Cooling (Station Ref: C7) was temporarily suspended since 22
October 2014 with respect to the formation of temporary reclamation zone TS3
and was resumed from 1 February 2018 onwards with respect to the completion of
removal of temporary reclamation zone.
2. Enhanced DO monitoring at
Monitoring station Ex-WPCWA SE was temporarily suspended from 31 August 2015
with respect to seawall reinstatement works and formation of active works area.
The Enhance DO monitoring at Ex-WPCWA SE was resumed on 11 May 2016 due to
completed section of seawall reinstatement works at Ex-PCWA.
4.3.23.
The
monitoring of dissolved oxygen are to be carried out 3 days per week, at
mid-flood and mid-ebb tides for 3 water depths (1m below water surface,
mid-depth and 1m above sea bed, except where the water depth less than 6m, the
mid-depth may be omitted. If the water depth be equal to or less than 3m, only
the mid-depth will be monitored).
Daily SS Monitoring and 24 hours Turbidity Monitoring System
4.3.24.
During
dredging of the sediment at the south-western corner of the Causeway Bay
Typhoon Shelter, daily monitoring of suspended solids and 24 hour monitoring of turbidity
at the cooling water intakes (C6 and C7) shall be
conducted.
4.3.25.
The 24 hours monitoring of turbidty at the cooling water
intakes (C6 and C7) shall be established by setting
up a continuous water quality monitoring station in front of the intakes during
the dredging activities. The monitoring system include the turbidity sensor and
data logger which is capable of data capturing at every 5 minutes. The data sahll be downloaded daily and compared with the Action and Limit level determined
during the baseline water qualtiy monitoring at the cooling water intake
locations.
Additional Dissovled oxygen Monitoring FOR CULVERT L WATER DISCHARGE
FLOW
4.3.26.
In
response to the Condition 2.18 of the Environmental Permit no. EP-356/2009
requiring that a silt curtain / impermeable barrier system be installed to
channel water discharge flow from Culvert L to locations outside the embayment
area, a proposed replacement of the requirement with additional dissolved
oxygen monitoring has been conducted at three monitoring stations, namely A, B
and C between the eastern seawall of Central Reclamation Phase III and the
HKCEC Extension since November 2011 under EP-356/2009 so that DO level between
the eastern seawall of Central Reclamation Phase II and the HKCEC extension
could be continuously monitored.
4.3.27.
With respect to the
commencement of dredging works under HK/2012/08 and the installation of MTR
precast protection unit, the enhanced water quality monitoring for Culvert L
was temporarily suspended since 24 July 2013
4.3.28.
The
monitoring of dissolved oxygen are to be carried out once per week, at
mid-flood and mid-ebb tides for 3 water depths (1m below water surface,
mid-depth and 1m above sea bed, except where the water depth less than 6m, the
mid-depth may be omitted. If the water depth be equal to or less than 3m, only
the mid-depth will be monitored).
5.0.1.
The
environmental monitoring will be implemented based on the division of works
areas of each designed project managed under different contracts with separate
FEP applied by individual contractors. Overall layout showing work areas of
various contracts, latest status of work commencement and monitoring stations
is shown in Figure 2.1 and Figure 4.1. The monitoring
results are presented in according to the Individual Contract(s).
5.0.2.
In
the reporting month, the concurrent contracts are as follows:
Contract no. HY/2009/15- Central- Wan
Chai Bypass Tunnel (Causeway Bay Typhoon Shelter Section)
Contract no. HY/2010/08- Central- Wan
Chai Bypass Tunnel (Slip Road 8)
5.0.3.
As
confirmed by WDII RSS, the marine construction works under Contract HK/2009/01
have been completed since 24 July 2017, the monitoring association with
Contract HK/2009/01 and relevant reporting has been ceased in the reporting
month.
5.0.4.
As
confirmed by CWB RSS, the marine construction works under Contract HY/2009/15
and relevant reporting have been completed by 19 June 2017, the monitoring
association with Contract HY/2009/15 and relevant reporting has been ceased in
the reporting month.
5.0.5.
As
confirmed by CWB RSS, the seabed reinstatement works was resumed under Contract
HY/2009/15 at EX-PCWA area on 26 June 2019. The relevant noise monitoring
station monitoring stations namely M2b – Noon day gun area, M3a - Tung Lo Wan
Fire Station and relevant air quality monitoring stations namely CMA3a – CWB
PRE Site Office would be associated with Contract HY/2009/15 in the reporting
month.
5.0.6.
As
confirmed by CWB RSS, the marine construction works under Contract HY/2010/08
and relevant reporting have been completed by 21 September 2018, the air monitoring
stations namely CMA3a - CWB PRE Site Office and noise monitoring station namely
M2b – Noon day gun area and M3a - Tung Lo Wan Fire Station association with
Contract HY/2010/08 and relevant reporting has been ceased in the reporting
month.
5.0.7.
As
confirmed by WDII RSS, the marine construction works under HK/2012/08 and
relevant reporting have been completed by 2 January 2019, the air monitoring
stations namely CMA5b - Pedestrian Plaza, CMA6a – WDII PRE Office and noise
monitoring station namely M1a - Footbridge for Ex-Harbour Road Sports Centre
association with Contract HK/2012/08 and relevant reporting has been ceased in
the reporting month.
5.0.8.
As
confirmed by CWB RSS, the marine construction works under Contract HY/2009/19
and relevant reporting have been completed, the monitoring association with
Contract HY/2009/19 and relevant reporting has been ceased in the reporting
month.
5.0.9.
As
confirmed by CWB RSS, the seabed reinstatement works was resumed under Contract
HY/2010/08 at CBTS area on 7 August 2019. The relevant noise and air quality
monitoring station monitoring station namely CMA3a – CWB PRE Site Office, M2b –
Noon day gun area and M3a - Tung Lo Wan Fire Station would be associated with
Contract HY/2010/08 in the reporting month.
5.0.10.
Referring
to WDII RSS confirmation on the completion of marine works under HK/2009/02
within the EP-356 area on 30 September 2019, the relevant air quality and noise
monitoring stations namely CMA3a – CWB PRE Site Office, CMA4a - SPCA, and M1a –
Footbridge for Ex-Harbour Road Sports Centre would not be associated with
Contract HK/2009/02 in the reporting month.
5.0.11.
The
environment monitoring schedules for reporting month and coming month are
presented in Appendix 5.1.
5.0.12. The proposed division of noise
monitoring stations are summarized in Table 5.2 below.
Table 5.2 Noise Monitoring
Station for Contract nos. HY/2009/15 and HY/2010/08
Station |
Description |
M2b |
Noon-day gun
area |
M3a |
Tung Lo Wan
Fire Station |
5.0.13. As confirmed by CWB RSS, the seabed
reinstatement works was resumed under Contract HY/2009/15 at EX-PCWA area on 26
June 2019. The relevant noise monitoring station monitoring stations namely M2b
– Noon day gun area and M3a - Tung Lo Wan Fire Station would be associated with
Contract HY/2009/15 in the reporting month.
5.0.14. As confirmed by CWB RSS, the seabed
reinstatement works was resumed under Contract HY/2010/08 at CBTS area on 7
August 2019. The relevant noise monitoring station monitoring stations namely
M2b – Noon day gun area and M3a - Tung Lo Wan Fire Station would be associated
with Contract HY/2010/08 in the reporting month.
5.0.15. No action or limit level exceedances was
recorded in the reporting period.
5.0.16. Noise monitoring results measured
in this reporting period are reviewed and summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix
5.2.
5.2.1
The
proposed division of air monitoring stations are summarized in Table
5.7 below.
Table 5.7 Air
Monitoring Stations for Contract no. HY/2009/15 and HY/2010/08
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.2.2
As
confirmed by CWB RSS, the seabed reinstatement works was resumed under Contract
HY/2009/15 at EX-PCWA area on 26 June 2019. The relevant air quality monitoring
station monitoring station namely CMA3a – CWB PRE Site Office would be
associated with Contract HY/2009/15 in the reporting month.
5.2.3
As
confirmed by CWB RSS, the seabed reinstatement works was resumed under Contract
HY/2010/08 at CBTS area on 7 August 2019. The relevant air quality monitoring
station monitoring station namely CMA3a – CWB PRE Site Office would be
associated with Contract HY/2010/08 in the reporting month.
5.2.4
No action
or limit level exceedance was recorded in this reporting period.
5.2.5
Air
quality monitoring results measured in this reporting period are reviewed and
summarized.
5.3.1 Action and Limit level of water quality
monitoring was transited from wet season to dry season from 01 October 2019.
5.3.2 Water quality monitoring station C7 and
Enhance DO monitoring station C6 shall be associated with Contract HY/2010/08,
upon confirmation of marine construction works completion under Contract
HY/2009/15 at CBTS area and Ex-PCWA area since 19 June 2017.
5.3.3 Referring to CWB RSS confirmation on
the completion of marine construction activities within the Ex-PCWA area and
the completion of the post construction water quality monitoring, the
respective Enhance DO Monitoring within Ex-PCWA for monitoring station Ex-PCWA
SE and Ex-PCWA SW was temporarily suspended since 07 March 2017 ebb tide
onwards.
5.3.4 With respect to the reinstatement of
the silt screen system for Cooling Water Intakes P7, P8, P9 and WSD Water
Intake RW21, the respective water quality monitoring was reverted to the previous
monitoring location for Water Quality Monitoring Station RW21-P789 from water
quality stations RW21-P789 East (RW21-P789E) and RW21-P789 West (RW21-P789W)
from 25 January 2017 onwards.
5.3.5 With respect to the temporarily
suspension of marine construction works at WCR3 Area by Contract HK/2009/02,
the installed silt screen for intake group (P7, P8, P9 and WSD21) was removed
on 26 November 2016.
5.3.6 As advised by the Contractor of
HK/2009/01, all silt screen remains removal works at P1, P3, P4, P5 and C1 water
quality monitoring stations were completed on 8 May 2016.
5.3.7 With respect to the marine works
undertaken at WCR3 by Contract HK/2009/02, the respective water quality
monitoring station C1 associated with Contract HK/2009/01 was updated as in
association with Contract HK/2009/01 and Contract HK/2009/02.
5.3.8 With respect to the marine works
undertaken at CBTS by Contract HY/2010/08, the respective water quality
monitoring station C7 associated with Contract HY/2009/15 was updated as in
association with Contract HY/2009/15 and Contract HY/2010/08.
5.3.9 With respect to the marine works
undertaken at HKCEC2 by Contract HK/2012/08, the respective water quality
monitoring station WSD19, P1, P3, P4, and P5 were associated with Contract
HK/2012/08.
5.3.10 As confirmed by WDII RSS, the marine
construction works under Contract HK/2009/01 have been completed since 24 July
2017, the monitoring association with Contract HK/2009/01 and relevant
reporting has been ceased in the reporting month.
5.3.11 As confirmed by CWB RSS, the marine
construction works under Contract HY/2009/15 and relevant reporting have been
completed by 19 June 2017, the monitoring association with Contract HY/2009/15
and relevant reporting has been ceased in the reporting month.
5.3.12 Referring to CWB RSS confirmation on
the completion of marine works within the TS3 area and the completion of the
post construction water quality monitoring, the respective water quality
monitoring within TS3 for monitoring station C7 was temporarily suspended since
29 October 2018 onwards.
5.3.13 Referring to WDII RSS confirmation on
the completion of marine works under HK/2012/08 within the EP-356 area on 2
January 2019 and the completion of the post construction water quality
monitoring (From 2 January 2019 to 30 January 2019), the respective water
quality monitoring stations P1, P3, P4, P5 and WSD19 within EP-356 area was
temporarily suspended since 15 February 2019 onwards.
5.3.14 Referring to CWB RSS confirmation on
the resumption of marine works within the CBTS area. The respective water
quality monitoring within CBTS for monitoring station C7 was resumed since 7
August 2019 and associated with HY/2009/15 and HY/2010/08.
5.3.15 Referring to WDII RSS confirmation on
the completion of marine works under HK/2009/02 within the EP-356 area on 30
September 2019 and the completion of the post construction water quality
monitoring (From 30 September 2019 to 26 October 219), the respective water
quality monitoring stations C1 and RW21-P789 within EP-356 area was temporarily
suspended from 26 October 2019 onwards.
Table
5.11 Water quality Monitoring Stations for contracts with respect to remaining
DP3 work areas after the completion of DP5 & DP6 in 2012 and intake
diversion in 2013
Contract No. |
Remaining DP3 and work area(s) |
Relevant Water quality monitoring Stations, |
Division of WQM w.r.t tentative works commenced /
to be commenced |
HK/2009/02 |
WCR3, WCR4, TWCR4 |
RW21-P7892,
C11 |
Apr 2013 |
HK/2012/08 |
HKCEC2W, HKCEC2E |
WSD19, P13,
P33, P43, P53 |
Aug 2013 |
HY/2010/08 |
TCBR3, TCBR4 |
C64,
C74 (plus enhanced DO monitoring) |
Mar 2014 |
Remarks:
1. The water quality monitoring station C1 shall be associated with Contract No. HK/2009/02 upon commencement of marine works under DP3 at WCR3 area.
2. 4 intakes (re-provisioned Wanchai WSD intake, Great Eagle Centre, China Resources Centre & Sun Hung Kai Centre constructed adjacent to each other) taken as a single group for silt screen protection and monitoring. Re-provisioned intake reference: P1: HKCEC Phase 1; P3: APA, P4: Shui On; P5: Government Buildings (Wanchai Tower / Revenue Tower / Immigration Tower)
3. The water quality monitoring stations for WSD19, P1, P3, P4, P5 shall be associated with Contract No. HK/2009/01 prior to their transition to Contract HK/2012/08.
4. Enhance DO monitoring station C6 and water quality monitoring station C7 shall be associated with Contract HY/2010/08, upon confirmation of marine construction works completion under Contract HY/2009/15 at CBTS area and Ex-PCWA area since 19 June 2017.
5. Referring to CWB RSS confirmation on the completion of marine construction activities within the TS3 area and the completion of the post construction water quality monitoring, the respective Enhance DO Monitoring within TS3 for monitoring station C6 and C7 was temporarily suspended since 05 March 2018 onwards.
6. With respect to WDII RSS confirmation on the completion of
marine works under Contract HK/2009/01 since 24 July 2017, the association of
WQM station C1 under Contract HK/2009/01 has been ceased in the November 2017
reporting month.
7. Referring to CWB RSS confirmation on the completion of
marine works within the TS3 area and the completion of the post construction
water quality monitoring, the respective water quality monitoring within TS3
for monitoring station C7 was temporarily suspended since 29 October 2018
onwards
8. Referring to WDII RSS confirmation on the completion of
marine works under HK/2012/08 within the EP-356 area on 2 January 2019 and the
completion of the post construction water quality monitoring (From 2 January
2019 to 30 January 2019), the respective water quality monitoring stations P1,
P3, P4, P5 and WSD19 within EP-356 area was temporarily suspended since 15
February 2019 onwards.
9. Referring to WDII RSS confirmation on the completion of
marine works under HK/2009/02 within the EP-356 area on 30 September 2019 and
the completion of the post construction water quality monitoring (From 30
September 2019 to 26 October 219), the respective water quality monitoring
stations C1 and RW21-P789 within EP-356 area was temporarily suspended from 26
October 2019 onwards.
Contract no.
HY/2009/15 – Central- Wan Chai Bypass Tunnel (Causeway Bay Typhoon Shelter
Section) and HY/2010/08 - Central- Wan Chai Bypass Tunnel (Slip Road 8)
5.3.16 The proposed division of water
quality monitoring stations are summarized in Table 5.17 below:
Table 5.17 Water quality monitoring Stations for Contract no. HY/2009/15 and HY/2010/08
Station Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C7 |
Windsor House |
837193.7 |
816150.0 |
5.3.17 Referring to CWB RSS confirmation on
the resumption of marine works within the CBTS area. The respective water
quality monitoring within CBTS for monitoring station C7 was resumed since 7
August 2019 and associated with HY/2009/15 and HY/2010/08
5.3.18 One action level exceedance of Turbidity
during ebb tide on 11 March 2020 was recorded in this reporting month. After
investigation, the exceedance was not related to Project.
5.3.19 Three limit level exceedance of
Turbidity during flood tide on 9 March 2020 and during both flood and ebb tide
on 13 March 2020 were recorded. After investigation, the exceedances were not
related to Project.
5.3.20 Water quality monitoring results
measured in this reporting period are reviewed and summarized. Details of water
quality monitoring results and graphical presentation can be referred in Appendix
5.4.
Contract no.
HK/2009/02 - Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai
East
5.4.1
Details
of the waste disposal in the reporting period are summarized in Table
5.18.
Table 5.18 Details of Waste Disposal for Contract no.
HK/2009/02
Waste
Type |
Quantity
this month |
Cumulative
Quantity-to-Date |
Disposal
/ Dumping Grounds |
Inert
C&D materials disposed, m3 |
NIL |
313695.5 |
TKO137
/ TM 38 |
Inert
C&D materials recycled, m3 |
NIL |
18161 |
N/A |
Non-inert
C&D materials disposed, m3 |
NIL |
1515.103 |
SENT
Landfill |
Non-inert
C&D materials recycled, m3 |
N/A |
N/A |
N/A |
Chemical
waste disposed, kg |
NIL |
13860 |
SENT
Landfill |
Marine
Sediment (Type 1 – Open Sea Disposal), m3 |
NIL |
240222 (Bulk
volume) |
South
of Cheung Chau |
Marine
Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined
Marine Disposal) , m3 |
NIL |
146445 (Bulk
volume) |
East of
Sha Chau |
Contract
no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section)
5.4.2
Details
of the waste disposal in the reporting period are summarized in Table
5.19
Table 5.19 Details of
Waste Disposal for Contract no. HY/2009/15
Waste
Type |
Quantity
this month |
Cumulative
Quantity-to-Date |
Disposal
/ Dumping Grounds |
Remarks |
Inert
C&D materials disposed, m3 |
NIL |
141579.2 |
Tuen
Mun Area 38 |
NIL |
NIL |
65216 |
TKO137
FB |
NIL |
|
Inert
C&D materials recycled, m3 |
NIL |
8127.21 |
HY/2010/08 |
NIL |
NIL |
304 |
Ex-PCWA |
NIL |
|
NIL |
111.9 |
TS4 |
NIL |
|
Non-inert
C&D materials disposed, m3 |
NIL |
252.2 |
SENT
Landfill |
NIL |
Non-inert
C&D materials recycled, kg |
NIL |
299361.5 |
N/A |
NIL |
Chemical
waste disposed, kg |
NIL |
8,200 |
N/A |
NIL |
Marine
Sediment (Type 1 – Open Sea Disposal), m3 |
NIL (Bulk
Volume) |
156909 (Bulk
Volume) |
Cheung
Chau South |
Dredging
from TCBR1E / TCBR1W / TCBR2/ TCBR3 / TCBR4 / Maintenance dredging |
Marine
Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined
Marine Disposal) , m3 |
NIL (Bulk
Volume) |
327746 (Bulk
Volume) |
East of
Sha Chau / South of the Brothers |
Dredging
from TCBR1E / TCBR1W / TCBR2/ TCBR3 / TCBR4 / Maintenance dredging |
Marine
Sediment (Type 3 – Special Treatment / Disposal contained in Geosynthetic
Containers) m3 |
NIL (Bulk
Volume) |
12640 (Bulk
Volume) |
East of
Sha Chau / South of the Brothers |
Dredging
from TCBR1W / Maintenance dredging |
Marine
Sediment (Type 2 – Confined Marine Disposal), m3 |
NIL |
9350 (Bulk
Volume) |
East of
Sha Chau |
Dredging
from Eastern Breakwater of CBTS |
Marine
Sediment (Type 1 – Open Sea Disposal) , m3 |
NIL (Bulk
Volume) |
600 (Bulk
Volume) |
East
Sha Chau / South of The Brothers |
Dredging from Phase 3 Mooring Re-arrangement |
Marine
Sediment (Type 2– Confined Marine Disposal) , m3 |
NIL (Bulk
Volume) |
14,780 (Bulk
Volume) |
South
of The Brothers |
Dredging from Phase 3 Mooring Re-arrangement |
Marine
Sediment (Type 3 – Special Treatment / Disposal contained in Geosynehetic
Containers) , m3 |
NIL (Bulk
Volume) |
2,760 (Bulk
Volume) |
South
of The Brothers |
Dredging from Phase 3 Mooring Re-arrangement |
Contract no.
HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8)
5.4.3 Details
of the waste disposal in the reporting period are summarized in
Table 5.22
Table 5.22
Details of Waste Disposal
for Contract no. HY/2010/08
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
NIL NIL |
95973.148 33381.84 |
TM38 TKO137 |
Inert
C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed, m3 |
NIL |
NIL |
N/A |
Non-inert
C&D materials recycled, kg |
NIL |
NIL |
N/A |
Chemical
waste disposed, L |
NIL |
NIL |
N/A |
Marine
Sediment (Type 1 – Open Sea Disposal) |
NIL |
62559.4 |
South Cheung Chau / Brothers Island * |
Marine
Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined
Marine disposal) |
NIL |
28309.2 |
Brothers Island |
Marine
Sediment (Type 3 – Special Treatment) |
NIL |
7780 |
Brothers Island |
6.0.1.
The
Event Action Plan for construction noise, air quality and water quality are
presented in Appendix 6.1.
Contract no. HY/2009/15- Central- Wan Chai
Bypass Tunnel (Causeway Bay Typhoon Shelter Section) and HY/2010/08- Central-
Wan Chai Bypass Tunnel (Slip Road 8)
6.1.1
No action
or limit level exceedance was recorded in the reporting period.
Contract
no. HY/2009/15- Central- Wan Chai Bypass Tunnel (Causeway Bay Typhoon Shelter
Section) and HY/2010/08- Central- Wan Chai Bypass Tunnel (Slip Road 8)
6.2.1
No action
or limit level exceedance was recorded in this reporting period.
6.3.1 One action level exceedance of Turbidity
during ebb tide on 11 March 2020 was recorded in this reporting month. After
investigation, the exceedance was not related to Project.
6.3.2 Three limit level exceedance of
Turbidity during flood tide on 9 March 2020 and during both flood and ebb tide
on 13 March 2020 were recorded. After investigation, the exceedances were not
related to Project.
6.4.1
There was
no non-compliance from the site audits in the reporting period. The
observations and recommendations made in each individual site audit session
were presented in Section 8.
6.5.1
There was
no particular action taken since no non-compliance was recorded from the site audits
in the reporting period.
7.0.1.
According
to Condition 3.4 of the EP-356/2009, this section addresses the relevant
cumulative construction impact due to the concurrent activities of the current
projects including the Central Reclamation Phase III, Central-Wanchai Bypass
and Island Eastern Corridor Link projects.
7.0.3. According to the construction programme
of Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III
area, no works was conducted in March 2020 reporting period. In view of the
above, the cumulative construction impact due to the Central Reclamation Phase
III (CRIII) was not anticipated.
7.0.4. According to the construction programme
of Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern
Corridor Link projects, lighting column installation works under Wan Chai
Development Phase II was conducted at Wan Chai. The major construction
activities under Central-Wan Chai Bypass and Island Eastern Corridor Link
Projects were ventilation building ABWF works at Central; road works, drainage
improvement work, utility diversion works and landscape works at Victoria Park;
bridge noise enclosure installation works, road works, drainage works, soft
landscape works and ventilation building ABWF work at North Point area in the
reporting period. In addition, other non-Wan Chai Development Phase II,
Central-Wan Chai Bypass and Island Eastern Corridor Link projects were observed
undertaken at Wan Chai North and North Point area.
7.0.5. No significant air and noise
impact from construction activities was anticipated in the reporting month.
Besides, no project related exceedance was recorded during the air and noise
environmental monitoring events in the reporting month. Thus, it is evaluated
that the cumulative construction impact from the concurrent projects including
Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII),
Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) was
insignificant.
8.0.1. During this reporting month,
weekly environmental site audits were conducted for Contracts no. HK/2009/02, HY/2009/15 and
HY/2010/08. No non-conformance was identified during the site audits.
8.0.2.
Site
inspections for Contract no. HK/2009/02 were carried out during this reporting
period. No observation was found in the
reporting period.
8.0.3. Site inspections for Contract no. HY/2010/08
were conducted in the reporting period. No observation was found in the
reporting period.
8.0.4. Site inspections for Contract no. HY/2009/15
were conducted in the reporting period. No observation was found in the
reporting period.
Mitigation measures implemented to
prevent muddy discharge and surface runoff
8.0.5. With a view to ensure the adequacy and
effectiveness of measures to prevent the discharge of muddy water, including
surface run-off, from construction works, the following mitigation measures
were implemented by Contractor(s) in the reporting period:
Contract No. |
Mitigation Measures implemented |
HK/2009/02 |
·
The construction works in related to EP-356
was completed and the water quality impact in related to muddy water discharge
and surface runoff was not anticipated. |
HY/2010/08 |
·
Most of the land based construction works was
completed. Contractor will regular review the muddy discharge and surface
runoff concern depends on the remaining works |
HY/2009/15 |
·
Most of the land based construction works was
completed. Contractor will regular review the muddy discharge and surface
runoff concern depends on the remaining works |
9.0.1.
A public
complaint made to EPD on 18 December 2019 was received by ET on 12 March 2020.
The complainant reported that oil slick was spotted on sea surface outside Expo
Drive East next to the Hong Kong Convention and Exhibition Centre on 18
December 2019.
ET confirmed with the Resident Site
Staff that no construction activity was undertaken around the concerned
location under Contract HK/2009/02 on 18 December 2019 and the coastline of the
concerned area has already been handed over to other party.
9.0.2.
The
details of cumulative complaint log and updated summary of complaints are
presented in Appendix 9.1
9.0.3.
Cumulative
statistic on complaints and successful prosecutions are summarized in Table
9.1 and Table 9.2 respectively.
Table 9.1 Cumulative
Statistics on Complaints
Reporting Period |
No. of Complaints
|
Commencement works (Mar 2010) to last reporting month |
50 |
March
2020 |
0 |
Total |
50 |
Table 9.2 Cumulative Statistics on Successful Prosecutions
Environmental
Parameters |
Cumulative No.
Brought Forward |
No. of Successful
Prosecutions this month (Offence Date) |
Cumulative No.
Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1.
The
EM&A programme was carried out in accordance with the EM&A Manual
requirements, minor alterations to the programme proposed were made in response
to changing circumstances.
10.0.2.
The
scheduled construction activities and the recommended mitigation measures for
the coming month are listed in Table 10.1.
Table 10.1 Construction Activities and
Recommended Mitigation Measures in Coming Reporting Month
Contract No. |
Key Construction Works |
Recommended Mitigation Measures |
HK/2009/02 |
·
Nil |
·
Nil |
HY/2009/15 |
·
Nil |
·
Daily visual inspection of
silt screen to ensure the integrity and condition of silt screen. ·
Implement silt screen in
accordance with the associated plans submitted to EPD. ·
Ensure proper deployment of
silt curtain around marine construction works area. |
HY/2010/08 |
·
Nil |
·
Daily visual inspection of
silt screen to ensure the integrity and condition of silt screen. ·
Implement silt screen in
accordance with the associated plans submitted to EPD. ·
Ensure proper deployment of
silt curtain around marine construction works area. |